When Your Coder Misses a Deadline
Note: the links below are generic and don't reflect the links YOU would use for your particular project. Please refer to the email you received for the actual links.
Dear John Buyer,
The deadline for your project: "Integration from SQL Server to Oracle database"
at 8/13/2003 10:28:46 PM EDT is quickly arriving.
Hopefully Fred Coder has worked hard for you and is close to completing the
project to your 100% satisfaction. If this is the case, then I'm glad that your
project is progressing well. I hope you take the time soon to fully review their
final work so they can be awarded funds for it.
However, if Fred Coder is not able to complete your project 100% by the above
deadline, then you have 2 choices. You can either continue working with them or
cancel the project (and request a refund of unescrowed funds). However it is VERY
IMPORTANT that you read this email to learn how to do this properly. Doing so
incorrectly may cost you UNNECESSARY TIME and cause you UNDUE FRUSTRATION.
================================================
A) "Cancel the project"
================================================
As a buyer, you are entitled to receive 100% of what was agreed upon by the
deadline. If this doesn't happen and Fred Coder was responsible for the missed
deadline, then you may wish to cancel the project. You do this through the
arbitration process as detailed below.
What to do:
1) FIRST--AS SOON AS THE DEADLINE PASSES, DO NOT ASK Fred Coder TO FIX ANYTHING
IN THE DELIVERABLES (EVEN IF THEY ARE BROKEN) OR KEEP WORKING IN ANY WAY. (In
fact, you should just cutoff all communication with them). If you ask them to
fix items or keep working, you are telling them that the deadline you had
previously set no longer applies (see the arbitration rules of "implicit
extension"). Then, if you later want to cancel, you'll find you will be forced
in arbitration to set a 2nd true deadline. This will cost you unnecessary time
and undue aggravation. So if you really want to keep going, instead see the
steps for "Keep going" below. Otherwise, continue to step 2.
2) To cancel the project, please click on the dispute resolution link at:
http://www.RentACoder.com/RentACoder/misc/Feedback.asp?intTypeOfInquiry=7&lngBidRequestId=71883&lngBidId=777546Rent
a Coder will verify that the coder was at fault for not delivering 100% by the
deadline, via the process of arbitration. When confirmed you will receive a
refund of all un-awarded funds from escrow. (Please see rules of arbitration in
your contract for more details at http://www.RentACoder.com/RentACoder/SoftwareBuyers/SoftwareBuyerLegal.asp#arbitration).
If you feel a partial payment to the coder is appropriate, you can choose to
award one to them.
Please do be aware that if the coder is found to be at fault, we do have a
responsibility to other parties on the site to rate them accordingly. Also, if
you receive a refund of 100% of the funds, then you do not own copyright to what
was produced and must destroy all deliverables created by the coder. You can of
course choose to negotiate a partial payment with them for the copyright of what
they created, and we can oversee this in arbitration. Just mention this to your
arbitrator and they will make the necessary arrangements.
================================================
B) "Keep going"
================================================
There are many reasons why you may wish to continue working with Fred Coder past
the deadline. Perhaps outside factors beyond the Fred Coder's control caused a
deadline to slip and you wish to give them an additional chance. Or maybe you
can see that they are very close to completing the project and don't want to
lose the time you've invested. Or maybe you know that something you did caused
them to miss the deadline, and are willing to extend it. Whatever the reason,
here is how to do it:
What to do:
If you wish to continue working with Fred Coder...
1) FIRST--AS SOON AS THE DEADLINE PASSES, DO NOT ASK Fred Coder TO FIX ANYTHING
IN THE DELIVERABLES (EVEN IF THEY ARE BROKEN) OR KEEP WORKING IN ANY WAY...
UNTIL YOU'VE FOLLOWED ALL OF THE STEPS BELOW. If you ignore this advice, you
will be effectively telling the coder that the deadline you had previously set
no longer applies (see the arbitration rules of "implicit extension"). Then, if
you later want to cancel you'll find you will be forced in arbitration to set a
2nd true deadline. This will cost you unnecessary time and undue aggravation.
2) Place an onsite comment to Fred Coder and let them know:
a) That they missed the deadline but that you want to extend it (make sure to
specify a date, time and time zone).
b) If Fred Coder was fully or partially responsible for the missed deadline,
then give them your "commitment terms" for the extension (an explanation of this
important step and examples are below).
c) Ask for Fred Coder to agree to this onsite.
3) If they agree, then officially set the new deadline by clicking on "extend
delivery deadline" in your bid request control panel at http://www.RentACoder.com/RentACoder/misc/BidRequests/ShowBidRequest.asp?lngBidRequestId=71883#BuyerBidRequestControlPanel.
Hopefully they will now complete the work by the new deadline. But if for some
reason they don't, then you can choose to cancel or keep going by repeating the
process above.
4) (optional) If they don't agree to the terms, then place the project into
arbitration for a cancellation and refund (see #1 above).
========================
"commitment terms”
========================
If Fred Coder was negligent in any way, then creating "commitment terms" are
vitally important. The coder has already missed one deadline. They need to prove
that they are willing to increase their commitment, or else they are likely to
simply miss the next deadline in the same way. Some recommended “commitment
terms” are:
i) Firmly restate exactly what needs to be done.
Sometimes a coder's attention can "drift" over the course of the project,
causing them to lose focus. Doing this, refocuses them on exactly what is
expected and when. It also forces them to verify that they really understand
what you expect to receive and aren't just paying you lip service.
Example: “You’ve missed the deadline of 1/1. I’m extending it to 1/5 at 5PM EDT
because I like what I’ve seen so far. However I do expect the entire application
to be working by then. This includes the 4 bugs I’ve identified in our last
posts which are ... Please verify that you will complete this by then and I will
extend it.”
ii) Have the coder commit to greater contact:
If the coder has not been communicating well, you should increase the frequency
of required comment postings and the deliverables they've completed at the time,
to increase their effort and commitment to your project.
Example: “You’ve been absent and not responding for too long to this point and
now you have missed the deadline. If we are to continue I will need you to
provide twice a week updates to me…that includes both a report of what you’ve
done and the code you’ve completed at that time. If I don’t receive those I’ll
be putting this into arbitration for cancellation, so please don’t agree unless
you’re serious about finishing this up completely.”
iii) Mini milestones
This is a good tactic to use if the coder didn't finish a lot of the work they
originally promised, and you are unsure if they can finish it all. You don't
wish to invest a huge chunk of time into finding out however. To avoid this,
split the remaining work that is to be done into mini-milestones...detailing
what needs to be done by what date. This forces the coder to either start
finishing things on time, or face an earlier arbitration and terimination.
Example: "You have missed the deadline of 1/1 with a number of incomplete
features. This project has 3 parts remaining. If you wish me to extend this
deadline, you will have to complete part 1 by 1/2 5PM EDT, part 2 by 1/4 5PM EDt,
and part 3 by 1/5 5pm EDT. Please verify that you will complete this by then and
I will extend this project."
=============================
As usual, if you have any questions, concerns or issues, you can call or email
any facilitator at Rent a Coder at anytime for clarification (contact
information is below).
Sincerely,
Zoe Edgington
Rent a Coder Facilitator
Phone: (813) 908-9029
Fax: (813) 960-1495
P.S. If you respond to this email, please do not remove the following
information below in your reply so I can more quickly process your email.
Thanks.
Screen Name: John Buyer
Buyer on bid request: http://www.RentACoder.com/RentACoder/misc/BidRequests/ShowBidRequest.asp?lngBidRequestId=71883
Created on: 7/17/2004 5:41:02 PM EDT
|
|